So today we were expecting to see some section of the house plastered, but when we arrived no a single piece of plaster was installed. This was a pretty big disappointment we really hoped to see some progress, its like we get one item fixed per few days and then no progress.
I noticed that they had levelled or should i say attempted as there is still a 7mm gap between trusses!!, and the area in the hallway next to Bed3 hasn't even been attempted. I will be letting the SS know that I won't accept handover with a non level ceiling so he has more interest in fix it now.
Also sitting in our Garage was our stacking sliding door that had been returned now with new black tape on its fascia, I pealed a little bit back and could not see the original chip, but found another spot in the top corner that had be chipped thou alot smaller. I also noticed that they didn't fix the bottom track of the frame where it was chipped, this is getting beyond a joke.
The plumbing hasn't been siliconed in the wall correctly, I asked the SS when I was there last Friday if he could do this and he said no problem, then I reminded him on Tuesday and its still not done. I guess I'll have to just do it myself on the weekend as I'm not having banging pipes in my walls.
Some new plumbing work had been done in the last few days where the main incoming gas pipe has been run and fitted off. As we were leaving we also noticed that they have fixed the mortar colour on the Garage bricks, I can't even tell the difference!
One thing seems to have been done today. Rendering for the Front Master Bed Window Casements
The bedroom reveals haven't been fixed or even attempted. SS said he would get the carpenter to come back and fix them all. Not one has been touched.
|
Casement coverings on Front Windows |
|
Master Bed Window Rendered |
|
More Render |
|
The Fixed the rip in insulation in the Garage |
|
Door Frame is back... but still scratched at the bottom?!?! |
|
I hope they don't think they can leave this in there.... |